Construction Updates

Construction Map – May 2024

November 12, 2024

Dried-In: Done

Escalators: 4 installed – 2 on each end

Elevators: 2 public, 2 service – 1 is installed

HVAC: Units are in place and will be turned on when the weather dictates now that the Coliseum is dried-in.

Permanent Power: In the process of being finalized.

Framing: We are currently framing the interior spaces.

  • Suites are done
  • Video Room is done
  • Snack Bar is dome
  • Atrium Bar is being worked on
  • Lounge is being worked on
 

Exterior Concrete:

  • Started pouring the NE Plaza between the Coliseum and the planters
  • South side planters are taking shape
  • Loading Dock has been poured
 

The street around the Coliseum has been removed and grading / paving will start as weather permits

June 20, 2024

  • The last concrete pour is later this month – the remaining 1/3 of the coliseum floor and the final portion of the covered concourse.
  • The larger pieces of infrastructure like HVAC and power distribution are in place.
  • Escalators are scheduled for mid-July.
  • We are projected to be “fully closed in” by Fair time.

April 5, 2024

City leaders gathered for the Topping-Out Ceremony of the MAPS 3 and 4 OKC Fairgrounds Coliseum. Prior to the ceremony, attendees were invited to sign a large banner that will hang from the rafters of the new coliseum.

February 9, 2024

December 5, 2023

November 10, 2023

The majority of the concourse level concrete has been poured with the exception of the north section, Area C, which is scheduled to be completed very soon. Approximately half of the low roof concrete has been completed with Area D to be poured on November 21 and Area C on December 12, which will complete the elevated concrete deck structure. The truss support columns are underway and perimeter framing began on November 6. The arena wall is scheduled to be complete by the middle of November. Precast seating installation is scheduled to begin on November 27 and continue for four weeks. These are the currently scheduled dates, but all are subject to change due to weather and materials.

October, 19 2023

Construction on the OKC Fairgrounds Coliseum continued during the 2023 Oklahoma State Fair. Fairgoers were extremely tolerant of the inconvenience caused by the construction footprint at Gate 6. The public was largely happy to see progress made on the much-needed replacement to the Jim Norick Arena, and fortunately so, as we will be existing under these conditions through the 2024 Oklahoma State Fair. The current schedule calls for the OKC Fairgrounds Coliseum to open in mid-2025.

May 24, 2023

Watch an interesting timelapse video of the demolition of the Jim Norick Arena lobby below.

February 23, 2023

On Wednesday, February 22, the Mayor, other city officials, and invited guests took part in the official groundbreaking ceremony for the new OKC Fairgrounds Coliseum. The $126 million project is funded through MAPS 3, MAPS 4, hotel/motel tax revenue, and other funding sources.

Construction is scheduled to be complete in 2025. When completed, the 216,164 square foot coliseum will be operated by Oklahoma State Fair, Inc. The Jim Norick Arena will continue to host events, just as it has since 1965, until the new coliseum opens.

The MAPS 3 and 4 Fairgrounds Coliseum will feature seating for more than 7,000 with a variety of seating configurations. Included in the venue will be a lounge, suites, a full-serve restaurant along with several upscale concession areas, an A/V Suite, and a sophisticated catwalk system.

Check back for updates as this project progresses.